PJM Proposes New Requirements to Prevent Grid-Disrupting Data Center Disconnections

PJM Interconnection on Nov. 16 proposed new reliability requirements for data centers and other large computational facilities to prevent unexpected transfers from grid electricity to onsite generation during transmission disturbances. The proposal, submitted to the Federal Energy Regulatory Commission, would establish voltage and frequency ride-through standards requiring these facilities to remain connected to the grid during certain disturbances. The requirements aim to limit abrupt changes in electricity demand that could threaten grid reliability.

The filing follows several unexpected load transfer events in PJM’s territory. On July 22, nearly 3.9 gigawatts (GW) of data center demand unexpectedly shifted from utility supply to onsite generators following a routine transmission disturbance, marking the largest such event in PJM’s history. The sudden transfer affected system voltage, frequency, power flows, and generator operations in the Dominion transmission zone and across the Eastern Interconnection. Although PJM’s control center managed the event, the scale and speed of the transfers raised significant reliability and safety concerns. Earlier incidents in the Dominion zone involved unexpected transfers of approximately 1,500 megawatts (MW) in July 2024 and February 2025.

Under the proposal, PJM would establish a new category of Large Computational Loads covering facilities with electricity demand of 50 MW or more. The definition conforms with standards under development by FERC and the North American Electric Reliability Corporation to address the reliability challenges associated with large computing facilities and is consistent with other grid operators’ approaches. It reflects the grid operator’s assessment of emerging definitions for large loads and computational loads being considered by industry organizations and transmission providers.

PJM currently serves approximately 10 GW of large computational load and forecasts additions of up to 30 GW by 2030. The proposed standards would apply to existing and new facilities through amendments to PJM’s tariff. New facilities would need to demonstrate compliance as a condition of interconnection and operation, while existing facilities would have one year from the effective date to meet the requirements. Facilities entering commercial operation later would have one year from that date to comply.

PJM proposes Jan. 16, 2027, as the effective date for the new ride-through requirements, which would apply to both existing and future large computational facilities. The grid operator also plans to work with stakeholders on additional performance requirements, including ramp-rate standards, informed by operating experience, technical studies and future federal regulatory guidance.