PJM Approves Fourth Project Under Expedited Grid Connection Program
PJM Interconnection on Nov. 10 approved a fourth project under its expedited interconnection process, advancing efforts to bring new generation capacity online as electricity demand increases across its 13-state region. The latest approval covers a 500-megawatt battery storage facility proposed by Little Blue Solar in Beaver County, Pennsylvania, within the Allegheny Electric Cooperative Transmission System…...